Status & documents
The record, the draft conditions and the sources
A dated account of the application, what is draft and what is adopted, the work that settles each requirement, and where to read every source. Verified against the City’s record on October 5, 2026.
The record
What has happened, and what comes next
| Date | Step | What happened | Source |
|---|---|---|---|
| Oct. 5, 2020 | Planned Development approved | The City Commission approved the Willow Lakes Planned Development, a mixed-use village on this property. | City staff report |
| Mar.–June 2026 | Application materials | A concept plan (Bohler Engineering, March 27), an environmental assessment (EW Consultants, May), and a traffic memo and water and sewer memo (June) were submitted with the rezoning application. | City packet |
| Aug. 14–20, 2026 | Agency review | The St. Lucie Transportation Planning Organization (Aug. 14), County Public Works (Aug. 19) and the City’s technical review (Aug. 20, eleven questions to the applicant) commented on the application. | City packet |
| Aug. 20–Sept. 20, 2026 | Public comment | The City received 85 written submissions, one conditionally supporting the rezoning and 84 opposed. See the questions residents are asking. | Correspondence record |
| Sept. 17, 2026 | Planning Board meeting | The Board asked staff to research how data centers should be classified and regulated, and recommended that the City Commission discuss it. The applicant then asked to table the rezoning to a date uncertain, and the Board agreed. If the application returns, the City gives new public hearing notice. | Agenda · Video |
| Sept. 29, 2026 | Revised draft conditions | The applicant prepared a revised draft of conditional-use standards for large-scale data centers for discussion with the City. | Below |
| Oct. 5, 2026 | City Commission meeting | No data-center item was on the agenda. The Planning Board minutes for September 17 were not yet posted. | AgendaQuick |
| Next | Staff research and Commission discussion | Staff research on data-center classification and a City Commission discussion. No date is set. The Planning Director said the application’s return depends on that work. | Meeting video |
| If the application returns | Public hearings | New notice, a Planning Board recommendation and a City Commission decision. | City code Sec. 125-133 |
Draft and adopted
What is in effect, and what is proposed
In effect today
Adopted law, rates and code
- Fla. Stat. §366.043: large-load customers bear their own cost of service (July 1, 2026).
- Fla. Stat. §373.262 and §373.239: water-use permitting for large-scale data centers (July 1, 2026).
- Fla. Stat. §163.326: local land-use authority preserved (May 7, 2026).
- Fla. Stat. §288.075: confidentiality of economic-development records, as amended in 2026.
- FPL’s Large Load Contract Service, approved by the Public Service Commission on January 22, 2026 (order).
- City code: a 0.5 footcandle limit on light spillover (Sec. 125-315(j)), landscape screening where commercial or industrial land adjoins residential or open space (Sec. 123-37), and general noise limits that do not apply to uses in industrial districts (Sec. 26-37 to 26-41).
Proposed, not adopted
The applicant’s revised draft conditions
Dated September 29, 2026. They apply only if the City adopts them in an approval. The table below lists them, with the numbers still to be set.
Still to be set in the draft: the sound limits in dBA and dBC at the property line and at residential boundaries; the cap on routine municipal drinking water for cooling; and the width of the landscape buffer.
The draft conditions
The draft would allow a large-scale data center only as a conditional use in the I‑1 light industrial district and only if it meets every condition below. “Large-scale data center” has the meaning in Fla. Stat. §373.203. The 50-megawatt threshold decides whether that definition applies and is not a separate test.
| Topic | The draft condition |
|---|---|
| Location and electric service | Within 1,000 feet of existing electrical infrastructure able to serve the use, shown by co-location with 500 kV lines or a substation, plus written confirmation from the serving utility, or an agreement with it under §366.043, that the load can be served. A letter from at least one independent fiber provider confirming access. |
| Sound | Limits on continuous operation at the project property line and at residential and sensitive-use boundaries, in dBA and dBC (one-hour average), with separate day and night limits at residential boundaries. Baseline ambient measurements before operation, periodic testing by a qualified acoustical professional, and confirmation by the City’s acoustical consultant. |
| Water | Compliance with §373.262 and water-district permits. A long-term cooling-water strategy that does not impair existing public supplies. Routine municipal drinking water for cooling prohibited or limited to a set amount. For an on-site reservoir or reclaimed supply, a plan covering capacity, evaporation, drought, make-up water, discharge, water quality and emergencies, with periodic testing and reporting, including sealed water-balance testing. |
| Setbacks | Measured from the building wall or equipment pad to the nearest property line of the protected use. Residential: 300 ft for buildings, 400 ft for generators and major mechanical equipment. Schools, child care, hospitals with inpatient care, nursing homes and assisted living: 500 ft for both. Non-industrial commercial: 200 and 300 ft. Setbacks do not apply between parcels inside the same approved campus. |
| Height and buffers | Buildings no taller than 65 feet, not counting screened rooftop mechanical equipment, lightning protection, communications equipment and utility equipment. A landscape buffer on residential and sensitive-use boundaries designed to be substantially opaque year-round within three growing seasons. Generators, cooling equipment, substations and service yards visible from a public road, home or protected use are screened. |
| Lighting | Fixtures that minimize spill. Project illumination no higher than 0.5 footcandle at the project property line. A final photometric plan showing fixture locations, mounting heights, color temperature, controls and calculated spillover. |
| Generators and batteries | Combustion generation limited to emergencies, commissioning, scheduled maintenance and required testing, never routine power, peak shaving or economic dispatch. Routine testing Monday to Friday, 10 a.m. to 4 p.m., excluding legal holidays, with documented exceptions for law, permits, manufacturer protocol, utility direction or emergencies. No more units tested at once than the approved protocol reasonably needs. Acoustic enclosures, air permits, fuel-storage and spill-prevention compliance, and operating and testing records kept five years. Battery storage is not subject to generator hours and remains subject to fire, building, electrical, hazardous-material and emergency-response requirements. |
| Approval in stages | Conditional use sets the approved development envelope (maximum building area, height, anticipated electric load, on-site generation, cooling capacity, water demand and equipment areas), the conceptual site plan, principal access, setbacks and conditions. Final site plan adds utility, architectural, landscape, lighting, water, sound, traffic and emergency-response design for each phase. Building permits confirm code compliance. Conditions continue through operation. |
| Application contents | Development plan with maximums; electric-service evidence; fiber plan; sound study; water and cooling narrative; generation and fuel narrative; landscape and lighting plans; emergency-response narrative for fire, battery and fuel, and hazardous-material leaks; construction-management narrative; decommissioning narrative for fuels, batteries and major equipment. |
| Fiscal and public benefit | A fiscal-impact analysis may be requested for planning. A public-benefit analysis, with a community-benefit package covering education, job creation, training and community investment. |
Engineering and review
The work that sets each requirement
Each study below determines a specific requirement, is reviewed by a named body and comes due at a defined step.
| Work | What it determines | Reviewed by | When |
|---|---|---|---|
| Water balance and hydrogeologic review | How much water is withdrawn, evaporated, replaced and returned, and the effect on groundwater, which sets the amounts permitted | South Florida Water Management District; the City | With the water-use permit application, which needs a hearing; the draft requires the cooling plan at conditional use |
| Sound study | Existing background sound, including I‑95, and modeled campus sound, which settles where limits are set | The City’s acoustical consultant | With the conditional-use application (draft); compliance tests after opening |
| System-impact study and service agreements | The load, the interconnection and who pays for each part | FPL, under its PSC-approved rate | Before service begins; utility confirmation with the application (draft) |
| Stormwater plan and environmental resource permit | Drainage design, flood protection and wetland impacts | South Florida Water Management District; the City | Before construction |
| Updated traffic analysis | Net new trips and any access or intersection improvements | The City, St. Lucie County, the Transportation Planning Organization and FDOT | With the site plan; already requested by the Planning Organization and County Public Works |
| Fire-district capacity review | Equipment, staffing, water supply, access and training the campus needs | The fire district | With the site plan and building permits; the emergency-response plan comes with the application (draft) |
| Generator air permit | Emission limits and operating terms | Florida Department of Environmental Protection | Before generators are installed |
| Fiscal-impact analysis | Net revenue against the cost of public services | The City | May be requested at conditional use (draft) |
Take part
How to follow the process and be heard
Follow
- City agendas, packets and minutes: AgendaQuick, Planning Board. Meeting video: City video archive.
- As of October 5, 2026 no data-center item was on a City Commission agenda. The Commission’s October 12 day meeting, October 19 meeting and October 27 workshop were listed without agendas.
- Planning Department, 100 North U.S. 1, Fort Pierce. planning@cityoffortpierce.com, 772-467-3737. Ask to be notified of hearings and refer to PZZAM2026-00002.
Be heard
- Send comments to the Planning Department at the address above, and speak at any public hearing once one is noticed.
- Ask the Willow Lakes team a question at info@devcon-enterprises.com or in the FAQ.
- Local businesses, schools, training providers and workers can register interest.
Sources
Sources and documents
Law, regulators and the City’s own records come first, then independent research, then journalism for context, then utility statements. Letters from the public show what residents are asking, and developer materials show what Willow Lakes proposes and estimates.
| Source | What it covers |
|---|---|
| Chapter 2026-65, Laws of Florida | The 2026 act that created §163.326, §366.043 and §373.262 and amended §288.075, §373.203 and §373.239. Signed May 7, 2026. |
| §366.043; §373.262; §163.326; §288.075; §212.08(5)(r); §196.1995 | Large-load tariffs, water-use permitting, local authority, record confidentiality and tax treatment. |
| FPL tariff, Section 8; PSC Order PSC-2026-0022-S-EI; FPL newsroom | Large Load Contract Service terms, PSC approval and FPL’s October 1, 2026 filing. |
| South Florida Water Management District; environmental resource permits; FDEP, Levee–Midway line | Water-use and environmental permitting, and the 500 kV line from FPL’s Midway Substation. |
| City of Fort Pierce: Sept. 17 agenda; meeting video; agenda packet, 947 pages | The staff report (pp. 822–838), draft covenant (pp. 840–842), agency comments (pp. 917–925), environmental assessment, concept plan and traffic and water memos. |
| Loudoun County: tax, land use, noise, energy, water, public safety, workforce, standards, lessons | The county’s own data, finances, land-use history and standards work. |
| Brookings (Bahar and Wright, updated Aug. 10, 2026); Virginia JLARC; LBNL energy report; LBNL / Brattle price trends | Jobs, wages and home prices; jobs per facility, water, energy and noise; national electricity and water use; drivers of retail prices. |
| Henrico County; Henrico housing trust; New Albany; Louisa County; Washington Department of Revenue workgroup | Outcomes in other host communities. |
| Virginia SCC; Georgia PSC; PUCO and AEP Ohio; Utah Division of Water Rights; Loudoun Water | How other regulators handle large-load costs and water reporting. They do not govern Florida. |
| The Atlantic, June 12, 2026; Kentucky Power; Georgia Power | Context and utility statements, attributed to their authors. |
Documents
City record
Planning Board agenda, September 17, 2026 City of Fort Pierce · items 6c and 6d · View
Meeting video with transcript City of Fort Pierce · View
Agenda packet (947 pages, about 300 MB) Staff report · draft covenant · agency comments · applicant materials · View PDF
Applicant materials
Employment brief, October 8, 2026 Developer estimate · permanent and construction jobs and salaries · View PDF
Public correspondence
Every opposition letter, indexed by concern 84 letters, with links · contact details blacked out · Open
Letter of conditional support, August 29, 2026 Port St. Lucie technology educator · View PDF
Figures that differ between documents
| Topic | The documents | Used on this site |
|---|---|---|
| Acreage | City staff report 200.23 acres; County Property Appraiser 200.3 acres; some earlier materials 203.6 acres. | About 200 acres |
| Traffic | The 2020 analysis counts 37,828 daily trips for the approved Planned Development; a 2026 memo cites 37,297. | The 2026 figure for the comparison, with the applicant’s estimate of 22,920 |
| Electric service area | The City staff report lists the Fort Pierce Utilities Authority service area; that authority’s own comment says the site is outside its electric and water areas. | FPL owns the transmission lines and the substation at the site; the retail electric provider for the address is to be confirmed |