Status & documents

The record, the draft conditions and the sources

A dated account of the application, what is draft and what is adopted, the work that settles each requirement, and where to read every source. Verified against the City’s record on October 5, 2026.

The record

What has happened, and what comes next

DateStepWhat happenedSource
Oct. 5, 2020Planned Development approvedThe City Commission approved the Willow Lakes Planned Development, a mixed-use village on this property.City staff report
Mar.–June 2026Application materialsA concept plan (Bohler Engineering, March 27), an environmental assessment (EW Consultants, May), and a traffic memo and water and sewer memo (June) were submitted with the rezoning application.City packet
Aug. 14–20, 2026Agency reviewThe St. Lucie Transportation Planning Organization (Aug. 14), County Public Works (Aug. 19) and the City’s technical review (Aug. 20, eleven questions to the applicant) commented on the application.City packet
Aug. 20–Sept. 20, 2026Public commentThe City received 85 written submissions, one conditionally supporting the rezoning and 84 opposed. See the questions residents are asking.Correspondence record
Sept. 17, 2026Planning Board meetingThe Board asked staff to research how data centers should be classified and regulated, and recommended that the City Commission discuss it. The applicant then asked to table the rezoning to a date uncertain, and the Board agreed. If the application returns, the City gives new public hearing notice.Agenda · Video
Sept. 29, 2026Revised draft conditionsThe applicant prepared a revised draft of conditional-use standards for large-scale data centers for discussion with the City.Below
Oct. 5, 2026City Commission meetingNo data-center item was on the agenda. The Planning Board minutes for September 17 were not yet posted.AgendaQuick
NextStaff research and Commission discussionStaff research on data-center classification and a City Commission discussion. No date is set. The Planning Director said the application’s return depends on that work.Meeting video
If the application returnsPublic hearingsNew notice, a Planning Board recommendation and a City Commission decision.City code Sec. 125-133

Draft and adopted

What is in effect, and what is proposed

In effect today

Adopted law, rates and code

  • Fla. Stat. §366.043: large-load customers bear their own cost of service (July 1, 2026).
  • Fla. Stat. §373.262 and §373.239: water-use permitting for large-scale data centers (July 1, 2026).
  • Fla. Stat. §163.326: local land-use authority preserved (May 7, 2026).
  • Fla. Stat. §288.075: confidentiality of economic-development records, as amended in 2026.
  • FPL’s Large Load Contract Service, approved by the Public Service Commission on January 22, 2026 (order).
  • City code: a 0.5 footcandle limit on light spillover (Sec. 125-315(j)), landscape screening where commercial or industrial land adjoins residential or open space (Sec. 123-37), and general noise limits that do not apply to uses in industrial districts (Sec. 26-37 to 26-41).

Proposed, not adopted

The applicant’s revised draft conditions

Dated September 29, 2026. They apply only if the City adopts them in an approval. The table below lists them, with the numbers still to be set.

Still to be set in the draft: the sound limits in dBA and dBC at the property line and at residential boundaries; the cap on routine municipal drinking water for cooling; and the width of the landscape buffer.

The draft conditions

The draft would allow a large-scale data center only as a conditional use in the I‑1 light industrial district and only if it meets every condition below. “Large-scale data center” has the meaning in Fla. Stat. §373.203. The 50-megawatt threshold decides whether that definition applies and is not a separate test.

TopicThe draft condition
Location and electric serviceWithin 1,000 feet of existing electrical infrastructure able to serve the use, shown by co-location with 500 kV lines or a substation, plus written confirmation from the serving utility, or an agreement with it under §366.043, that the load can be served. A letter from at least one independent fiber provider confirming access.
SoundLimits on continuous operation at the project property line and at residential and sensitive-use boundaries, in dBA and dBC (one-hour average), with separate day and night limits at residential boundaries. Baseline ambient measurements before operation, periodic testing by a qualified acoustical professional, and confirmation by the City’s acoustical consultant.
WaterCompliance with §373.262 and water-district permits. A long-term cooling-water strategy that does not impair existing public supplies. Routine municipal drinking water for cooling prohibited or limited to a set amount. For an on-site reservoir or reclaimed supply, a plan covering capacity, evaporation, drought, make-up water, discharge, water quality and emergencies, with periodic testing and reporting, including sealed water-balance testing.
SetbacksMeasured from the building wall or equipment pad to the nearest property line of the protected use. Residential: 300 ft for buildings, 400 ft for generators and major mechanical equipment. Schools, child care, hospitals with inpatient care, nursing homes and assisted living: 500 ft for both. Non-industrial commercial: 200 and 300 ft. Setbacks do not apply between parcels inside the same approved campus.
Height and buffersBuildings no taller than 65 feet, not counting screened rooftop mechanical equipment, lightning protection, communications equipment and utility equipment. A landscape buffer on residential and sensitive-use boundaries designed to be substantially opaque year-round within three growing seasons. Generators, cooling equipment, substations and service yards visible from a public road, home or protected use are screened.
LightingFixtures that minimize spill. Project illumination no higher than 0.5 footcandle at the project property line. A final photometric plan showing fixture locations, mounting heights, color temperature, controls and calculated spillover.
Generators and batteriesCombustion generation limited to emergencies, commissioning, scheduled maintenance and required testing, never routine power, peak shaving or economic dispatch. Routine testing Monday to Friday, 10 a.m. to 4 p.m., excluding legal holidays, with documented exceptions for law, permits, manufacturer protocol, utility direction or emergencies. No more units tested at once than the approved protocol reasonably needs. Acoustic enclosures, air permits, fuel-storage and spill-prevention compliance, and operating and testing records kept five years. Battery storage is not subject to generator hours and remains subject to fire, building, electrical, hazardous-material and emergency-response requirements.
Approval in stagesConditional use sets the approved development envelope (maximum building area, height, anticipated electric load, on-site generation, cooling capacity, water demand and equipment areas), the conceptual site plan, principal access, setbacks and conditions. Final site plan adds utility, architectural, landscape, lighting, water, sound, traffic and emergency-response design for each phase. Building permits confirm code compliance. Conditions continue through operation.
Application contentsDevelopment plan with maximums; electric-service evidence; fiber plan; sound study; water and cooling narrative; generation and fuel narrative; landscape and lighting plans; emergency-response narrative for fire, battery and fuel, and hazardous-material leaks; construction-management narrative; decommissioning narrative for fuels, batteries and major equipment.
Fiscal and public benefitA fiscal-impact analysis may be requested for planning. A public-benefit analysis, with a community-benefit package covering education, job creation, training and community investment.

Engineering and review

The work that sets each requirement

Each study below determines a specific requirement, is reviewed by a named body and comes due at a defined step.

WorkWhat it determinesReviewed byWhen
Water balance and hydrogeologic reviewHow much water is withdrawn, evaporated, replaced and returned, and the effect on groundwater, which sets the amounts permittedSouth Florida Water Management District; the CityWith the water-use permit application, which needs a hearing; the draft requires the cooling plan at conditional use
Sound studyExisting background sound, including I‑95, and modeled campus sound, which settles where limits are setThe City’s acoustical consultantWith the conditional-use application (draft); compliance tests after opening
System-impact study and service agreementsThe load, the interconnection and who pays for each partFPL, under its PSC-approved rateBefore service begins; utility confirmation with the application (draft)
Stormwater plan and environmental resource permitDrainage design, flood protection and wetland impactsSouth Florida Water Management District; the CityBefore construction
Updated traffic analysisNet new trips and any access or intersection improvementsThe City, St. Lucie County, the Transportation Planning Organization and FDOTWith the site plan; already requested by the Planning Organization and County Public Works
Fire-district capacity reviewEquipment, staffing, water supply, access and training the campus needsThe fire districtWith the site plan and building permits; the emergency-response plan comes with the application (draft)
Generator air permitEmission limits and operating termsFlorida Department of Environmental ProtectionBefore generators are installed
Fiscal-impact analysisNet revenue against the cost of public servicesThe CityMay be requested at conditional use (draft)

All approvals that follow rezoning

Take part

How to follow the process and be heard

Follow

  • City agendas, packets and minutes: AgendaQuick, Planning Board. Meeting video: City video archive.
  • As of October 5, 2026 no data-center item was on a City Commission agenda. The Commission’s October 12 day meeting, October 19 meeting and October 27 workshop were listed without agendas.
  • Planning Department, 100 North U.S. 1, Fort Pierce. planning@cityoffortpierce.com, 772-467-3737. Ask to be notified of hearings and refer to PZZAM2026-00002.

Be heard

  • Send comments to the Planning Department at the address above, and speak at any public hearing once one is noticed.
  • Ask the Willow Lakes team a question at info@devcon-enterprises.com or in the FAQ.
  • Local businesses, schools, training providers and workers can register interest.

Sources

Sources and documents

Law, regulators and the City’s own records come first, then independent research, then journalism for context, then utility statements. Letters from the public show what residents are asking, and developer materials show what Willow Lakes proposes and estimates.

SourceWhat it covers
Chapter 2026-65, Laws of FloridaThe 2026 act that created §163.326, §366.043 and §373.262 and amended §288.075, §373.203 and §373.239. Signed May 7, 2026.
§366.043; §373.262; §163.326; §288.075; §212.08(5)(r); §196.1995Large-load tariffs, water-use permitting, local authority, record confidentiality and tax treatment.
FPL tariff, Section 8; PSC Order PSC-2026-0022-S-EI; FPL newsroomLarge Load Contract Service terms, PSC approval and FPL’s October 1, 2026 filing.
South Florida Water Management District; environmental resource permits; FDEP, Levee–Midway lineWater-use and environmental permitting, and the 500 kV line from FPL’s Midway Substation.
City of Fort Pierce: Sept. 17 agenda; meeting video; agenda packet, 947 pagesThe staff report (pp. 822–838), draft covenant (pp. 840–842), agency comments (pp. 917–925), environmental assessment, concept plan and traffic and water memos.
Loudoun County: tax, land use, noise, energy, water, public safety, workforce, standards, lessonsThe county’s own data, finances, land-use history and standards work.
Brookings (Bahar and Wright, updated Aug. 10, 2026); Virginia JLARC; LBNL energy report; LBNL / Brattle price trendsJobs, wages and home prices; jobs per facility, water, energy and noise; national electricity and water use; drivers of retail prices.
Henrico County; Henrico housing trust; New Albany; Louisa County; Washington Department of Revenue workgroupOutcomes in other host communities.
Virginia SCC; Georgia PSC; PUCO and AEP Ohio; Utah Division of Water Rights; Loudoun WaterHow other regulators handle large-load costs and water reporting. They do not govern Florida.
The Atlantic, June 12, 2026; Kentucky Power; Georgia PowerContext and utility statements, attributed to their authors.

Documents

City record

Planning Board agenda, September 17, 2026 City of Fort Pierce · items 6c and 6d · View

Meeting video with transcript City of Fort Pierce · View

Agenda packet (947 pages, about 300 MB) Staff report · draft covenant · agency comments · applicant materials · View PDF

Applicant materials

Employment brief, October 8, 2026 Developer estimate · permanent and construction jobs and salaries · View PDF

Public correspondence

Every opposition letter, indexed by concern 84 letters, with links · contact details blacked out · Open

Letter of conditional support, August 29, 2026 Port St. Lucie technology educator · View PDF

Figures that differ between documents

TopicThe documentsUsed on this site
AcreageCity staff report 200.23 acres; County Property Appraiser 200.3 acres; some earlier materials 203.6 acres.About 200 acres
TrafficThe 2020 analysis counts 37,828 daily trips for the approved Planned Development; a 2026 memo cites 37,297.The 2026 figure for the comparison, with the applicant’s estimate of 22,920
Electric service areaThe City staff report lists the Fort Pierce Utilities Authority service area; that authority’s own comment says the site is outside its electric and water areas.FPL owns the transmission lines and the substation at the site; the retail electric provider for the address is to be confirmed